Installation, Testing and Commissioning of LT Panels
Confirm cable entry direction (top/bottom) and foundation bolt.
Connect incoming and outgoing power cables as per approved drawings.
Ensure correct cable lugging, ferruling, and glanding.
Visual inspection for damages, loose hardware, and obstructions.
Verify control wiring, relay logic, and functional sequences.
Ensure proper operation of indicators, meters, and alarms.
Handover as-built drawings, manuals, and test reports.
Train end-users on operation and maintenance.
Shutdown & Breakdown maintenance
Reduces unexpected failures.
Improves long-term reliability and equipment life.
Ensures safety compliance.
Unplanned and reactive.
Often requires quick response to restore operations.
Annual Maintenance Contract (AMC)
Benefits of an AMC
Reduces downtime
Ensures regular maintenance
Predictable maintenance costs
Longer equipment lifespan
Priority support
Operation & maintenance Contracts of all LT Panels
Scope of Work
Preventive Maintenance
Breakdown / Corrective Maintenance
Responsibilities of the Service Provider
Contract Types
Comprehensive AMC (Annual Maintenance Contract)
Non-Comprehensive AMC
Optional Add-On Services
ACB & VCB Repairing And Servicing
ACB Servicing :
Complete cleaning of the breaker
Inspection of arcing contacts, main contacts & arc chutes
Lubrication of mechanical parts
Megger testing / insulation resistance check
Secondary injection testing of protection relays
Functional testing of closing, tripping, and spring charging mechanisms
Replacement of worn-out parts (coils, springs, auxiliary contacts, motors, etc.)
Calibration of release units (ETR/Microprocessor-based trip units)
HV/LV Insulation Testing Up-to 5000V, Like: Cable Fault | HT Panel, Transformer Issues
✔ HT / LT Cables
1.1kV, 3.3kV, 6.6kV, 11kV, 22kV, 33kV cables
Detects:
Moisture ingress
Insulation deterioration
Joint/termination failures
Partial discharge risks
Cable sheath damage
Excavation, Cable Laying, Cable Termination & Cable Jointing
1. Excavation
In cable projects, excavation Ensure proper depth and protective layers for underground cables
2. Cable Laying
underground, in ducts, or on cable trays.
3. Cable Termination
4. Cable Jointing
Earth PIT Testing's
🔧 Earth PIT Testing Important?
Ensures electrical safety
Prevents electric shock hazards
Protects equipment from lightning and fault currents
Ensures compliance with electrical standards (IS 3043, IEEE 80, IEC 60364)
Transformer Oil Filtration & BDV Report, With All Transformer Maintenance
✔ Transformer oil filtration
✔ BDV test conducted before and after
✔ Silica gel replaced / checke
✔ Breather clean
✔ Bushings clean
✔ Oil leakage check
✔ Radiators clean
✔ Cooling fans/pumps test
✔ OLTC (if available) check
✔ Buchholz relay test
✔ Temperature gauges check
✔ Earthing inspectation
✔ Conservator oil level check